I drove by the site this morning, not much activity though. However, I noticed framing for a big new sign on the SE corner of Commissioners and Don Roadway.
From
Actra website
There are some renderings there also.
FILMPORT UPDATE November 7, 2006
Many people have been asking about progress at FILMPORT. Here’s an update:
Work started on August 30th. Site preparation is nearly complete.
TEDCO is presently excavating and cleaning up contaminated areas of the site. This work will continue through November.
Pile driving for the deep foundations will commence on November 20th once TEDCO clean-up crews are out of the way.
Foundation work will continue through the Winter months. The erection of steel structures will begin in early Spring, with concrete wall and roof sections following in late Spring.
Some sound stages should be ready for occupancy by December, 2007. All of Phase 1 will be ready for occupancy by Spring 2008.
Watch for our website to be launched shortly at
www.FILMPORT.ca. A place-holder site is up now but the new site will have current information and updates, including a web-cam to track progress.