Good to see the pedestrian promenade on west side of Parliament Slip is getting worked on. According to the FARM Committee report last week, the work on the Slip should be done by or in Q1 2025

1732377952583.png
 
Last edited:
The WT Board documents for their meeting next week note:

Construction continues to fill in the head of Parliament Slip and create a new dockwall. Current work includes the placement of infill material and the installation of rock berm and will enable the extension of Queens Quay East and realignment of Parliament Street to support the future road network and planned light rail transit in the area. Construction is expected to be complete by January 2025.
That’s just the berm right? They’re not going to have a road laid by February.
 