Toronto One Crosstown Towers I, II, III, and The Crest | 129.86m | 39s | Aspen Ridge | Core Architects

Taken today, April 10th, 2024. Glass cladding installation has started, and here's what it looks like

IMG_0693.jpg
IMG_0690.jpg
IMG_0689.jpg
 
Taken today, April 22nd, 2024. The Westernmost tower seems to be on its final floor now

View attachment 558238
Once the western tower tops out in April / early May more resources will be diverted to the Middle and Eastern buildings. Spring / Summer weather is when they work the quickest so expect these to top out rather quickly.

Western Tower Approximately 31 out of 32 = 97% (Occupancy - Jan 2025 - 9 Months to go) - At this pace, should top out some point late April early May
Middle 20 out of 39 = 51% (Occupancy March 2025 - 11 months to go) - At this pace, should top out some point in July
Eastern 23 out of 34 stories = 68% (Occupancy (April 2025 - 1 year to go) - Should top out some point in June
 