Great update here: https://www.minto.com/gta/new-condo...-Update-Working-On-Up-At-Westside~m_1104.html
"...the concrete form work team are now in a cycle that sees them completing 1 floor of structure every 6 days. The 8th floor slab of the Westside and B-side Towers was completed on October 23rd, and work has started on the 9th floor slab, which will be the Plunge Social rooftop lounge! Once the 9th floor is completed, you will begin to see the separate Westside and B-side towers rise up as two separate towers from the podium rooftop level...We have also started the installation of the temporary hoist... the first sections of the metal panel cladding arrive on site later in November. In the meantime, the structural steel trade and the drywall trade are beginning to complete some of the back-up assemblies needed to support the windows at the ground floor Level."
"...the concrete form work team are now in a cycle that sees them completing 1 floor of structure every 6 days. The 8th floor slab of the Westside and B-side Towers was completed on October 23rd, and work has started on the 9th floor slab, which will be the Plunge Social rooftop lounge! Once the 9th floor is completed, you will begin to see the separate Westside and B-side towers rise up as two separate towers from the podium rooftop level...We have also started the installation of the temporary hoist... the first sections of the metal panel cladding arrive on site later in November. In the meantime, the structural steel trade and the drywall trade are beginning to complete some of the back-up assemblies needed to support the windows at the ground floor Level."