Toronto KING Toronto | 57.6m | 16s | Westbank | Bjarke Ingels Group

November 4 - End of Day. More cladding / glazing done along the King Street frontage. Also, new progress in the mechanical infrastructure - water piping runs being installed for the Second Floor areas.

20241104_122404.jpg



20241104_161849.jpg


New footings for the cladding:

20241104_122555.jpg


Why it is called a Spyder Crane:

20241104_161927.jpg


New mechanical rough-in - water piping runs for the Second Floor:

20241104_122617.jpg


20241104_162036.jpg
 
Last edited:
November 5: Some overall King Toronto building views, plus one image of the ongoing cladding / glazing installation along the King Street frontage. This portion of the installation (ground level along the King Street frontage between the west entrance to the courtyard and the driveway) is now complete, and it looks like installation activities will next proceed down the west side of the courtyard entrance. Overall building views - all remaining forming support equipment has now been deinstalled and removed from the site.

20241105_145642.jpg


20241105_152306.jpg


20241105_145407.jpg


20241105_155538.jpg


20241105_145915.jpg
 

Attachments

  • 20241105_145646.jpg
    20241105_145646.jpg
    436.5 KB · Views: 24
November 13: Glazing and cladding installation has over the past few days been taking place in a couple of areas which are quite difficult to see and photograph from the perimeter of the site. First to be done was the ground floor wall along the south side of the interior courtyard between the centre and west entryways. The first photo is of the west portion of this area. The second area, underway today, is of the east section of King Toronto's King Street frontage - pretty much completely hidden by the hoarding that extends from the site's east boundary to the opening for Gate 1.

Cladding along the western portion of courtyard's south wall.

20241113_102246.jpg


Work on the King Street section of the facade:

20241113_102439.jpg


20241113_102449.jpg


20241113_102512.jpg


Prep for the installation along the east wall of the courtyard entrance.

20241112_132615.jpg


Arrival of more cladding

20241112_132641.jpg


20241112_132643.jpg


20241112_132700.jpg


Bracing for reinstallation of the heritage wall sections that have been preserved off site for the duration.

20241113_102320.jpg
 
November 15 - Cladding and glazing continue to be installed along the King Street facade progressing from the east property line on an east to west basis. First photo, with the top of the sections peeking out over the King Street sidewalk hoarding, is from yesterday, the second photo from this afternoon - progress from one day to the next is visible.

Thursday:

20241114_164024.jpg


Friday:

20241115_152623.jpg
 

Attachments

  • 20241114_164049.jpg
    20241114_164049.jpg
    321.7 KB · Views: 21
November 18 Afternoon. Installation of the cladding / glazing units along the ground floor of the building's entire King Street facade is now complete. The centre section of the King Street frontage consists of heritage structure facades that were retained in place, so will only need new glass in the existing building window openings.

Installation of the cladding is proceeding along the east wall of the opening to the courtyard. Once installation wraps around the courtyard all that will be left to be done for the ground floor will be the south east section of the courtyard wall, including the wrap around the back to where the heritage building has been retained. Then we should see installation activities starting on the Second Floor.

Heading south into the courtyard:

20241118_144951.jpg


Interior courtyard ground floor areas still to be done. New glazing visible at the left edge of the photo immediately below.

20241118_153147.jpg


20241118_153210.jpg


A lot of cladding / glazing sections on site and ready for installation

20241118_153524.jpg




20241118_144529.jpg
 

Attachments

  • 20241118_144523.jpg
    20241118_144523.jpg
    378.9 KB · Views: 16

Back
Top