drum118
Superstar
Was planning on doing something else today, but extra work show up. Once I finished it, still time to do things and decided to shot Hurnontario.
Was going to start at Elm and saw no excavator working south of Elm and that must be the one parked on Elm. Crews were placing the pylons onto the medium to allow all 3 lanes to be in service.
Looking at the trees walking toward Burnhamthrope, it look like most the trees could stay for the north stop. There would be some issues for the south stop on the north side of Burnhamthrope, but still workable. I noticed a number of tree stump from Burnhamthorpe to Robert Speck and a number of trees didn't look good. Best to cut them down now. 4 of the 5 trees north of Robert Speck in good shape, younger and easy to transport to another site. The 5th is dead.
About a dozen trees or so will be have to be cut down between Rathburn and the 403 for the elevated bridge over 403.
Work will have to take place under Hurontario Bridge to protect 403 traffic before the medium can be remove.
The pylons stop on the medium at Kingsbridge as I continue north to Nahani Way and shot the 2 tower sites there.
On my way back to catch a 103 bus at Eglinton, crews were installing pylons on the medium on the south side and a crew was just starting to go north of Eglinton placing pylons on the medium.
Was going to start at Elm and saw no excavator working south of Elm and that must be the one parked on Elm. Crews were placing the pylons onto the medium to allow all 3 lanes to be in service.
Looking at the trees walking toward Burnhamthrope, it look like most the trees could stay for the north stop. There would be some issues for the south stop on the north side of Burnhamthrope, but still workable. I noticed a number of tree stump from Burnhamthorpe to Robert Speck and a number of trees didn't look good. Best to cut them down now. 4 of the 5 trees north of Robert Speck in good shape, younger and easy to transport to another site. The 5th is dead.
About a dozen trees or so will be have to be cut down between Rathburn and the 403 for the elevated bridge over 403.
Work will have to take place under Hurontario Bridge to protect 403 traffic before the medium can be remove.
The pylons stop on the medium at Kingsbridge as I continue north to Nahani Way and shot the 2 tower sites there.
On my way back to catch a 103 bus at Eglinton, crews were installing pylons on the medium on the south side and a crew was just starting to go north of Eglinton placing pylons on the medium.