Main Line Track Removal (Update)
The existing main line track will be removed to facilitate guideway construction. This work involves cutting and breaking down the existing track into smaller manageable pieces and removing it from the rail corridor.
Barrie GO train service has increased substantially as of September 8. Due to the proximity of the existing main line track that is being removed to the new diversion track that trains are running on, this work must be performed overnight while trains are not running in order to keep crews safe.
This work will now take place during night shifts for the duration of the work period. Crew will be working overnight on Wednesday, September 16, Thursday, September 17 and Friday, September 18. Ancillary activities may take place during the day time.