Well, the tunneling drive was pretty much flawless. So the early arrival is good news. The project ends up with float that wasn't needed. One would expect that costs will be lower than they might have been. Whether ML gets the savings, or the contractor does, I don't know.
The extraction shaft may be a different contract than the tunnel itself. For that matter, the critical path may lie in how fast the conveyor and other utilities associated with the TBM's can be removed from the length of the tunnel. The TBM extraction itself may not be critical to the project schedule.
- Paul
The extraction shaft may be a different contract than the tunnel itself. For that matter, the critical path may lie in how fast the conveyor and other utilities associated with the TBM's can be removed from the length of the tunnel. The TBM extraction itself may not be critical to the project schedule.