Under the settlement agreement, CTS has committed to substantially complete the project’s construction and systems scope by the end of September 2022. The in-service date for passenger revenue services may be several months later and Metrolinx and TTC will continue to track CTS’s performance during 2022 to determine when the Eglinton Crosstown Line will open for passengers.
These large transit projects are very complex with significant delivery and schedule risks that we continue to actively manage together with CTS. While challenging, the Eglinton Crosstown Line is both a hugely exciting and a very significant transit addition in the city.
The Eglinton Crosstown Line will transform transit in Toronto along its 19km route, stopping at 25 stations, connecting Toronto from the east to the west, with journeys 60% faster than before, and providing direct connections to TTC subway Line 1, 2 and 3, three GO lines and also the UP Express.