I found out recently that we're not supposed to ask that question because people will post automatically if they know anything. Just letting you know why you got an angry react.Any updates ?
Interesting calculation. Not sure (not an architect or engineer) but I assume the high rise part might go faster as the podium and midrise Covered more area? I guess we can guesstimate once it reaches floor 10 and 11?I assume the aim is top out Block 5A by the end of the year before the snow starts which seems doable. 23 floors in 7 months.
Podium 4/4 floors (100%)
Midrise 4/9 Floors (44%)
High Rise 4/27 Floors (15%)
Usually the rule of thumb is 1-1.5 floor a week on average. With 23 floors left to go that is about 30-35 weeks aka 8 ish monthsInteresting calculation. Not sure (not an architect or engineer) but I assume the high rise part might go faster as the podium and midrise Covered more area? I guess we can guesstimate once it reaches floor 10 and 11?