Toronto CIBC SQUARE | 241.39m | 50s | Hines | WilkinsonEyre

  • Thread starter Suicidal Gingerbread Man
  • Start date
It will go as far as the concrete wall being poured adjacent to the tracks
 
8C16E836-687A-46BF-9E02-20AD7BE76B9C.jpeg
 

Attachments

  • 8C16E836-687A-46BF-9E02-20AD7BE76B9C.jpeg
    8C16E836-687A-46BF-9E02-20AD7BE76B9C.jpeg
    254.6 KB · Views: 676
Friday's New Toy

Westside Story: Yesterday pour, today the pop and tomorrow a lift.

IMG_1007.jpg


A closer look at the core and introducing our new toy ELLIOT. A small crane was added midweek just north of the blue concrete pumping machine. I don't know what Elliot will be doing yet, but I'm sure he'll be a valuable member of the core team. In this shot, you may also see they have popped the forms after yesterdays concrete pour.

IMG_1009.jpg


A jump-jack was added to both Crane#1 and Cran#2 earlier in the week.

IMG_1011.jpg


Here's a youtube animated video showing how it all works


Eastside Story: Still making slow progress on the Ground Level 01 of the bus depot, most of the forming work has been dedicated to the north crash wall.

East.jpg
 

Attachments

  • IMG_1007.jpg
    IMG_1007.jpg
    387.6 KB · Views: 1,015
  • IMG_1009.jpg
    IMG_1009.jpg
    306.8 KB · Views: 1,030
  • IMG_1011.jpg
    IMG_1011.jpg
    291 KB · Views: 1,023
  • 0 bytes · Views: 0
  • East.jpg
    East.jpg
    404.6 KB · Views: 1,015
Friday's New Toy

Westside Story: Yesterday pour, today the pop and tomorrow a lift.

View attachment 157543

A closer look at the core and introducing our new toy ELLIOT. A small crane was added midweek just north of the blue concrete pumping machine. I don't know what Elliot will be doing yet, but I'm sure he'll be a valuable member of the core team. In this shot, you may also see they have popped the forms after yesterdays concrete pour.

View attachment 157545

A jump-jack was added to both Crane#1 and Cran#2 earlier in the week.

View attachment 157547

Here's a youtube animated video showing how it all works


Eastside Story: Still making slow progress on the Ground Level 01 of the bus depot, most of the forming work has been dedicated to the north crash wall.

View attachment 157556
Stitched:
Untitled_Panorama1.jpg
 

Attachments

  • Untitled_Panorama1.jpg
    Untitled_Panorama1.jpg
    310.5 KB · Views: 1,014
Time for a Crane Lift. So Crane#1 has one section inserted just under the operator cab and feeling that the operator might need some extra support, a triangular support structure was attached to the building to keep it from wobbling. I'm sure Crane#2 will be treated the same in the near future.

IMG_1014.jpg
 

Attachments

  • IMG_1014.jpg
    IMG_1014.jpg
    296.3 KB · Views: 752