Toronto Cherry Place | 55.7m | 13s | Rekai | Montgomery Sisam

...documentation of a given project's stagnation maybe as important showing it's progression...even if just to let us know something is supposed to be built here. It's still news, IMO...and far better option than threads being bumped for those annoying "Any news?" questions.
 
Sooo... any news? 🥳
If you really want to know you could check the City Building Permit site yourself to see if the Permit Status has changed. (As I just did, I can report the main permit is unchanged as "Agreement in Process, the Drain and Site service says "Issuance Pending" which is, I think, unchanged too.)
 
Silliness above aside...............

Mech and Plumbing permits are ready to go when the cheque is submitted.

Shoring and New Build permits had a deficiency notice sent dated Dec 18th, 2024.

So there is activity on file, but the requisite permits for construction are not yet in place.
 