Site Plan Approval application submitted on December 17:

4926 BATHURST ST
Ward 6: York Centre


Site Plan Approval - Development of a new 26-storey building with residential area of 20275 sq.m. and street-related commercial, with a non-residential GFA of 920sq.m.
 
…and at last week's City Council, they did vote to send the City Solicitor off to the OLT hearing to oppose this. No indication of when the hearing is scheduled (the OLT still hasn't worked out how to present new appeals on their website since June of last year).

42
 
Last edited:
The case will be heard at the OLT starting March 20, 2023. Ten days have been set aside for the hearing.


42

A settlement offer on this one was adopted at the last meeting City Council.

Height reduced to 24s exclusive of MPH.

From the offer:

1671809786353.png

1671809824338.png


1671809846441.png


Offer link:


Revised Arch. Plans:


Oh, right..............renders:

1671809954553.png


1671809993073.png
 
A settlement offer on this one was adopted at the last meeting City Council.

Height reduced to 24s exclusive of MPH.

From the offer:

View attachment 447058
View attachment 447059

View attachment 447060

Offer link:


Revised Arch. Plans:


Oh, right..............renders:

View attachment 447061

View attachment 447062
So it got chopped down to 24 storeys and 1 fewer level of underground parking but has it been approved now?
 
Now that it's been about 2 1/2 months since it was approved, I have been wondering when we can expect to see the gas station closing/Tim Hortons. The development at Bathurst and Wilson has already begun demolition, but I'm not sure when its project will get going. There is a question about the clean-up process with the ground underneath the gas station. A planning friend of mine informed me that it might be a long process (10 years lol). I am not sure what to believe. Also, I cannot find any reference to the project by IBI group or Portal developments beyond the application and schematics.
 

Community Meetings​

Date:Feb 1, 2024Time:9:30 a.m.Location:Virtual Hearing / Council Chamber, North York Civic Centre, 5100 Yonge Street, M2N 5V7

I am a noob at this how is this project moving along considering the info provided?
 
Last edited:
The database has been updated to reflect the updated SPA / MV resubmission of December 2023. Changes are as follows:
  • Storey count increased from 24 to 29-storeys
  • Height increased from 78.05 to 96.55m
  • Total units increased from 259 to 349
Updated renderings:
PLN - Architectural Plans 2 of 2 - Architectural Plans_Part 2_4926 Bathurst Street-10.jpg

PLN - Architectural Plans 2 of 2 - Architectural Plans_Part 2_4926 Bathurst Street-9.jpg

PLN - Architectural Plans 2 of 2 - Architectural Plans_Part 2_4926 Bathurst Street-6.jpg

PLN - Architectural Plans 2 of 2 - Architectural Plans_Part 2_4926 Bathurst Street-7.jpg

PLN - Architectural Plans 2 of 2 - Architectural Plans_Part 2_4926 Bathurst Street-8.jpg
 
So staff wrangled the height down, the project was approved; but the dev snuck the height back in (and then some) through COA. Staff must be pissed LOL. Granted, they shouldn't have wasted everyone's time fighting for TWO FLOORS.
 