From just before the snow really started to fall and they were beginning to cover it up. Jan. 9th, 2024

20240109_085306.jpg
 
Finally got back up to take a look at this one. From this morning Jan. 30th, 2024. Looks like only part of the transfer slab has been poured, although I think the other portion might not need to carry as much weight due to the tower placement. I could be mistaken though as it looks similar.
I will be able to grab what will hopefully be the completed slab next week when I visit.