Mississauga 3600-3606 Hurontario Street | ?m | 50s | Edenshaw

Anyone have a recent up to date photo?
Try to get one today. Been on my do list the last week to do and yet to do it along with some others.
 
Dec 11
Mods Note:
The proposed development 3600 Hurontario Street consists of a 51-storey Condominium Apartment building with a total of 587 units and a Gross Floor Area (GFA) of36,498.2 square meters

The site going to committee of adjustment on Dec 14 to reduce parking from .8 to ,5 and visitors from .15 to .1 with the city opposing it. Gee!! only a short walk to the LRT stop and quick access to Sq One and Cooksville GO station or Port Credit station.

The south side where the drain and creek is has bee dug up to a point there is an trunk line running diagonal on about an 45 degree from the south east corner that connects to a box going under Hurontario St that is mostly bury at this time.

There was an easement apply for over a year ago or so that ran along the west side of the properly between the existing building to the west and the site. I guess it was for relocating that diagonal trunkline to connect to the new south end trunkline.

A few shots as the rest are being added to my backlog that just double in size with today 1.5 hour shooting secession.
133A3884.JPG
133A3887.JPG
133A3889.JPG
 
Jan 20
It was either last year or 2022 that an application was made for an easement along the west side of the site with no explanation for why and I see why now. The Cooksville Creek trunk line run across the site and it needs to be relocated to build on the site. The work taking place is the first phase of relocating the trunk line as well deal with a creek on the southside. Now the westside work is done, backfilling is underway and once done, work can start on the west side.

More up on my site
53493544092_d455fb5d1d_b.jpg

53494581603_68cb4b65e5_b.jpg

53493543872_f1c87df33e_b.jpg

53494850630_a33527ee52_b.jpg

53494850685_51ac85df8d_b.jpg

53493543347_38b6eb9d54_b.jpg
 
Feb 6
More up on my site

most of the southside has been backfill with work still taking place at each end before it can be completely buried.

Large pipe sections for the drain system to go along the west side are now on site and that could start next week or the following week, depending on the outstanding work still to be done. Once that work is completed, it will connect to the existing system with the current connect at Hurontario be disconnected. The current line will be removed when excavation for the new development gets underway at some future date or maybe remove once the new system is in place.
53515840049_edde8cf773_b.jpg

53515689933_6d1cbf86cf_b.jpg

53514634937_3ec3b75dfc_b.jpg

53515954380_e7032ecda2_b.jpg

53515521776_7379f18390_b.jpg

53514635122_922e66046a_b.jpg

53515690173_e44a83f3ef_b.jpg
 
Feb 22
The relocation of the trunk line is now completed, and it opens the door for the project to be marketed and then built.
53551727797_099ce9dd37_b.jpg

53552584451_7fcba4c8ba_b.jpg

53553031030_70c31b6cd8_b.jpg

53551728017_a12fefd2e8_b.jpg
53552924514_eccfaa74a6_b.jpg
 