Toronto 220 Lake Promenade | 97.28m | 30s | The Lake Promenade Co-Tenancy | BDP Quadrangle

No new renderings are updated in the database. The total unit count changes from 1473 units to 2021 units. The full bike parking changed from 1700 bike parking to 1642 bike parking.
 
No new renderings are updated in the database. The total unit count changes from 1473 units to 2021 units. The full bike parking changed from 1700 bike parking to 1642 bike parking.

🤔 What's going on here..........

~+550 units only 2 months after the initial submission?

- Bike parking goes down, contrary to City by-law

No cover letter or planning addendum explaining......
 
Last edited:
Now i'm very curious to know what in the planet is going on with this proposal, this is way too excessive for this site.
 
This thing's been chudding around since 2014. They're in no hurry and neither should anyone else be...

Which begs the question of why one sees a large change in the number of units only 2 months post-submission. That's relatively rare; and without the planning addendum or a cover letter, it feels kinda rushed.
 
Last edited:
5B201102-6EC1-434F-A84F-A063E94F39DA.jpeg
0C3D48F2-5489-436B-9B26-B6F071F5EAD0.jpeg


Info Sheets for Tenants on Rental Replacement policy, etc.
 
Some news on this one.

First, its the subject of an Appeals reporting, seeking staff to oppose this at the OLT, at the next meeting of EYCC:


From the above: (some of Planning's issues)

1732540679318.png

**

1732540711361.png

**

1732540763445.png

1732540800313.png

**

1732540849029.png


**

Some general concerns about excessive height and then...

1732540922676.png

**

1732540977763.png

**

1732541015670.png

1732541031701.png

**

1732541085640.png

1732541121864.png

1732541147688.png


And more if you follow the link.

@Paclo

Second item, the OLT hearing has been calendared for September 9th, 2025.
 