Toronto 199 Church | 124.5m | 39s | CentreCourt | Arcadis

Supporting docs reposted on Jan 6, 2021:



church.JPG
church2.JPG
 
Forecasted construction timeline:

Demolition: from March 2021 to June 2021;
Excavation and shoring: from June 2021 to December 2021;
Below grade formwork: from December 2021 to July 2022;
Above grade formwork: from July 2022 to November 2023;
Building envelope phase: from September 2022 to January 2024 2023; and
Interior finishes stage: from December 2022 to November 2024.

 
?are the above dates , official?? , and ?is there an exact date , demolition is starting ?
thank you , in advance

Yes, it's official, there is a link provided in the post to a City report.

The information in the report was supplied to the City, by the developer, in service of obtaining permission for a permit for a construction staging area (occupying a City road).

The dates are given as ranges, because the permit hasn't even been issued yet; it is going before Community Council for just that; further there is always an allowance for delays built into project timelines, which is why date ranges widen out further into the future.
 
Construction is anticipated to start in May:


CentreCourt and Parallax are partners on the 39-storey, 484-unit 199 Church Condos, which launched sales last July and has fewer than 10 per cent of its units still available. Construction is anticipated to start in May.
 
Fantastic to see work commence. Church needs a ton of work but is going to look substantially better in 6-7 years.
 

Back
Top