CONDOMINIUM BUILDING Proj: 9107384-4
Toronto, Metro Toronto Reg ON NEGOTIATED/PLANS COMPLETE
Ice Condo, Phase One, 16 York St, M5J 2Z2
$98,000,000 est
Start: June, 2010 Complete: October, 2013
Note: Sales and marketing are ongoing. Const Mgr is seeking building permits. Sub trades will be awarded sequentially from an Invited list. Shoring and excavation are underway. Construction start is expected June/July, 2010. Further update June, 2010.
Project: concrete foundation, cast-in-place concrete structural frame, structural steel frame, fuel fired heating system, proposed construction of a 55-storey condominium building with 453 suites. Units will range in size from 400 to 1,00 sq ft. The project will feature retail space at grade level and will be connected to the underground PATH system to Union station, Maple Leaf Square, the Air Canada Centre, Rogers Centre and the CN Tower.
Scope: 900,000 square feet; 55 storeys; 2 storeys below grade; 453 units; 2 hectares
Development: New
Category: Apartment bldgs
First report Fri Sep 04, 2009. Last report Fri Feb 12, 2010.
This report Mon Apr 05, 2010.
http://www.dailycommercialnews.com/...412964df39a7&projectid=9098331®ion=ontario
CONDOMINIUM APARTMENT BUILDING Proj: 9098331-5
Toronto, Metro Toronto Reg ON NEGOTIATED/WORKING DRAWINGS
Ice Condominium Phase Two, Bremner Blvd, York St, Lake Shore Blvd, M5J
$89,000,000 est
Start: March, 2011 Complete: July, 2014
Note: Working drawings are underway. Sales and marketing are ongoing. Const Mgr expects construction Spring, 2011 pending occupancy. All Sub trades will be secured from an Invited list. Further update early Winter, 2010.
Project: concrete foundation, concrete tilt-up structural frame, fuel fired heating system, proposed construction of a 65 storey condominium building a 2.8 acre site bounded by Bremner Street to the north, York Street to the east, and Lake Shore Boulevard to the south. The building will have retail space at grade and will be connected to the underground PATH system to Union Station, Maple Leaf Square, the Air Canada Centre, Rogers Centre and the CN Tower.Suites will range from 400 to 1,100 sq ft. The project will be connected by a podium to Phase One, a 55 storey condo building, followed under report number 9107384.
Scope: 850,000 square feet; 65 storeys; 4 storeys below grade; 647 units; 3 acres
Development: New
Category: Apartment bldgs; Retail, wholesale services
First report Fri Mar 27, 2009. Last report Fri Feb 12, 2010.
This report Mon Apr 05, 2010.