September 2008
Construction continues on schedule. Concrete slabs are being poured for floor levels 42 and 43 (mechanical floors). Curtain wall installation in the tower continues on levels 33, 34, 35 and 36 and will be completed in the podium. Elevator installation continues in the high rise, mid rise and service elevator banks. Mechanical and electrical trades continue with their rough ins throughout the tower floors including lighting, fire alarm and sprinkler systems. Installation of access flooring in the typical office floor areas will start and proceed up the building on levels 7, 8, 9, and 10. Installation of the exterior stone wall will be completed on the south side. Ground floor glazing will be complete. The feature stair in the podium on the Wellington Street side will be complete.