August 2008
Construction continues on schedule. Concrete slabs are being poured for floor levels 38, 39, 40 and 41. Forming and pouring of the podium will be completed. Curtain wall installation in the tower continues on levels 29, 30, 31 and 32 and will be completed in the podium area. Elevator installation continues in the high rise, mid rise and service elevator banks. Mechanical and electrical trades continue with their rough ins throughout the tower floors including lighting, fire alarm and sprinkler systems. Drywall board installation continues up the tower in the core areas including stairwells, mechanical and electrical rooms, washrooms and elevator lobby areas. The Ritz-Carlton is forming and pouring the eighth floor tower slab and will begin forming and pouring the ninth floor tower slab. Installation of mechanical and electrical work will continue from level P6 to level 6.