The current expected completion date is Jan 2027. How realistic is this given they are working on Floor 7/8 right now?
Thanks
 
Hi
The current expected completion date is Jan 2027. How realistic is this given they are working on Floor 7/8 right now?
Thanks
I wouldn't be booking any movers just yet.
 
A bit of a different angle for the third phase. I didn't realize till today that it was visible from this part of Elm Drive.
That is the smaller southern section of the development. If I am not mistaken it was added to the main tower after they bought out the last holdout parcel of land facing Hurontario. Actually they might’ve been prodded into buying that property by the city after the owner had a change of heart or realized they made a bad decision in holding out.
 
Hi
The current expected completion date is Jan 2027. How realistic is this given they are working on Floor 7/8 right now?
Thanks
Given they will be at the 13th floor by year end, this leaves 37 floors to go plus the mechanical floor. At a floor a week, you are looking around Oct 2026 before the building is top off with Summer of 2027 to see some move in. No cigar for a Jan 2027 date for move in on the main tower.

No idea how they will handle the 12 story tower for move in and going out on the limb you may see move in in the fall of 2026, but best to check with the your agent.
 
That is the smaller southern section of the development. If I am not mistaken it was added to the main tower after they bought out the last holdout parcel of land facing Hurontario. Actually they might’ve been prodded into buying that property by the city after the owner had a change of heart or realized they made a bad decision in holding out.