I emailed Remington with that exact question last month. Here is their answer:
Thank you for your email. When we went to market with Nexus North, Construction had not commenced and we were required to include a date for "Tentative Occupancy" as per Tarion Warranty Corporation. Since we have now commenced construction, and prior to 90 days ahead of the First Tentative Occupancy Date, we will be required to provide you with an updated Tentative Occupancy Date. Once the roof assembly is completed on the buildings, we will then be able to provide you with a Confirmed Occupancy Date. So, as it stands now, the First Tentative Date (August 2012) remains the same.
With respect to your second question, Nexus North and South commenced construction at the same time as the underground is shared. However, due to accessibility of the cranes on site, we needed to proceed with the South Tower about 1.5 months of work before the North Tower. Eventually, as the two towers are poured, focus will be directed back to the North Tower for finishing ahead of the South Tower.
I hope your concerns have been addressed.
Thank you.
Dorothy Dranitsaris-Carey
Client Care Manager, High Rise Division
The Remington Group Inc.
7501 Keele Street, Suite 100
Vaughan ON L4K 1Y2
Tel: 905-761-8200 x 307
Fax: 905-760-1147
email:
dcarey@remingtongroupinc.com
It appears based on the photos, Nexus South will be ready by Summer 2012...Which is funny because Nexus North was originally scheduled for Summer 2012 when we purchased it! Nexus South was originally scheduled for 2013.
Does anybody know what is going on here?? Has there been a revised construction completion date for these Nexus buildings??