The 2.5 km tunnel lines operate at 115KV and after some digging, on the internet, they are supplying 230KV cables.
Maybe the spools were delivery by train? Maybe they don’t have enough room in The Esplanade TS Yard? I counted over 40 spools. Maybe
@globalexpress has a better view on the count? Then I found four spools in the TS yard with one matching the ones by the tracks.
I can’t imagine they are installing 230KV lines in ducts on/near the tracks unless they are replacing the overhead lines. Are there any existing buried HV lines under ground in this area? Maybe the new Gardener or the OL Line or the Don flood protection work requires a tower or two to be relocated and they are burning the main feed.
After some more digging I found this
From the USCR TPAP Environmental Project Report of 2018.
I guess we have more fun stuff to watch.
View attachment 548941
View attachment 548929
View attachment 548930
View attachment 548931
View attachment 548932
View attachment 548933
View attachment 548934
View attachment 548935
View attachment 548936
View attachment 548937
View attachment 548938
View attachment 548939
View attachment 548940