    Toronto 2444 Yonge Street | 114.27m | 31s | First Capital | Hariri Pontarini

    Update - now 2 boring machines. Photos taken Nov 5.
  2. D

    Toronto Sixty Five Broadway | 132.89m | 39s | Times Group | Wallman Architects

    Sorry. Found those \"missing\" photos of 10-27-2023.
  3. D

    Toronto 2444 Yonge Street | 114.27m | 31s | First Capital | Hariri Pontarini

    Not sure what the smaller drilling equipment (second photo- north part of site) is doing, although the site had at least three of them at one time, so maybe that is almost complete. The first photo shows a large shoring equipment (south part of site), which I first saw about a week ago and now...
  4. D

    Toronto Sixty Five Broadway | 132.89m | 39s | Times Group | Wallman Architects

    Took more photos but this is the only one that took. East side of project can be seen in some of photos I took of 75 Broadway on the same day - 10-27-2023. This project, specifically the building at the rear, is progressing faster than any other I\'ve seen on this site.
  5. D

    Toronto 75 Broadway Avenue | 117.34m | 38s | Hazelview | WZMH

    Wondering what that wooden extension at the level of the adjacent old building is for - anyone? Taken 10-24-2023
  6. D

    Toronto Plaza Midtown | 107.89m | 34s | Plaza | BDP Quadrangle

    Nearing completion, including parkette work in last three photos. Taken 10-27-2023.
  7. D

    Toronto One Delisle | 155m | 44s | Slate | Studio Gang

    Looks like most of excavation, other than in one corner where an excavator with an extendable arm sits, is complete. With the very sandy soil on this site, crane should be rising soon, hopefully. The St. Clair and Yonge area has so many vacant stores or barren areas where demolition...
  8. D

    Toronto 346 Davenport | 36.27m | 9s | Freed | RAW Design

    Looks like this is complete. At least some occupancy has started.
  9. D

    Toronto Blue Diamond Condos and Foxbar Towns at Imperial Village | 88.08m | 28s | Camrost-Felcorp | Diamond Schmitt

    POPS still not complete but significant progress, in particular outside the former church structure. Let\'s hope it gets done before the snow flies.
  10. D

    Toronto Sixty Five Broadway | 132.89m | 39s | Times Group | Wallman Architects

    Taken 8-21-23. As usual a hive of activity. These are going up quickly. Already taller than the building under construction to the east, even though construction started much later.\r\n