Crazy amount of effort that goes into the construction of this building seemingly compared to other projects.
Since the mechanical levels (17&18) I have them averaging 8 days for the slabs and 4 days for the walls, and they've definitely been starting to pick up the pace...That's 6 working days a floor. For a concrete high rise structure, a decent pace.