How far down do they have to dig for the basement?
There will be four underground levels (plus a mezzanine/partial level that's mostly bike storage and PATH connection) where previously there was only one. Incredibly ambitious to keep the old exterior up when doing all that in behind and below!

42
 
There will be four underground levels (plus a mezzanine/partial level that's mostly bike storage and PATH connection) where previously there was only one. Incredibly ambitious to keep the old exterior up when doing all that in behind and below!

42



No wonder this project started out like gang busters, and really slowed down. Seems like a complicated job.
 
How many below grade levels is this building supposed to have? Im having trouble finding it anywhere, but I apologize if its been brought up already in this thread.
 