New to the AIC is this fairly ambitious, MTSA and YNSP inspired application for Yonge-Steeles area.

aka. @sunnyraytoronto 's turf!

What strikes me as ambitious is the 45s application does not have any major street frontage currently, being about a 1/2 block in from Yonge, currently amidst SFH.

With that, here's the App:

1660985013358.png



* Docs are Up *

1660985136394.png


1660985575801.png

Looking North along Yonge

1660985638195.png


1660985289046.png


1660985382985.png


1660985419514.png


1660985479436.png


1660985513777.png


1660985244816.png


From the Planning Rationale Report:

1660985773608.png


1660985979608.png


1660986075668.png


Comments:

Height may be viable in the medium term, but seems premature in the current context.

Podium is terrible, self-explanatory

Landscape Plan: ZERO trees on the property frontage. You must be kidding. Entirely non-compliant with City policy. (note trees in one of the renders above, but they aren't in the LP)

Parking Ratio seems high at ~0.5 for a site within a few hundred Meters of a proposed subway station, and a block from Yonge.
 
Last edited:
Decision Report - Approval Recommended to the next meeting of TEYCC:


@Paclo this one has had a modest hair cut to 43s; and has lost about 10M

Parking Ratio has also declined from 0.5 to 0.3

Gah! This is the second one in a row where the report describes a change in the building but there are no new Arch. Plans submitted.

What's going on here? Hmmmmm
 
Decision Report - Approval Recommended to the next meeting of TEYCC:


@Paclo this one has had a modest hair cut to 43s; and has lost about 10M

Parking Ratio has also declined from 0.5 to 0.3

Gah! This is the second one in a row where the report describes a change in the building but there are no new Arch. Plans submitted.

What's going on here? Hmmmmm
Planning staff probably can't keep up with the proposals at Yonge and Steeles!
 
Planning staff probably can't keep up with the proposals at Yonge and Steeles!

I just asked and got a reply.

TY to the person in question who shall remain anonymous.

City Planning is moving towards approving new zoning without requiring fully up-to-date Arch. Plans; these will only be required for Site Plan Approval.
 
Gah! This is the second one in a row where the report describes a change in the building but there are no new Arch. Plans submitted.

What's going on here? Hmmmmm

The new documents are dated December 2023. Changes below:
  • Height reduced from 145.1 to 140.65m
  • Storeys reduced from 45 to 43
  • Total residential units decreased from 544 to 516
  • Total vehicular parking reduced from 228 to 172

New renderings:
Architectural Plans (16)-403.jpg
Architectural Plans (16)-404.jpg
Architectural Plans (16)-405.jpg
Architectural Plans (16)-406.jpg
Architectural Plans (16)-407.jpg
Architectural Plans (16)-408.jpg
Architectural Plans (16)-409.jpg
Architectural Plans (16)-410.jpg
Architectural Plans (16)-411.jpg
Architectural Plans (16)-412.jpg
Architectural Plans (16)-413.jpg
Architectural Plans (16)-414.jpg
 
Was the lack of trees along the frontage fixed?

I assume we can’t know without the arch plans.

We have revised Arch. Plans; and we have street trees!

****

Approved at Council with amendments focused on offsite parkland dedication.
 