This report on the work at NPS is coming to the Government management Committee next week. See: http://app.toronto.ca/tmmis/viewAgendaItemHistory.do?item=2013.GM21.11
Project Elements and Schedule
The NPS project construction (including revitalization and State of Good Repair (SOGR) work) is divided into four phases with various project elements scheduled for completion from 2010 to 2014 and is summarized as follows:
Phase 1A was completed in May 2010 with the construction of the new City Hall
Podium Green Roof.
Phase 1 was completed in 2010-2011 as follows:
o replacement of the children's playground equipment (completed December 2010);
o new Skate Pavilion and Concession building (completed November 2011); and
o underground infrastructure work for other project elements, including electrical,
data, water, sewer, and gas site services (completed December 2011).
Phase 2 was completed in 2012 as follows:
o the new northwest vehicular laneway (completed February 2012);
o a nine-jet water fountain feature and new electrical and data hydrants in the middle
of the Square (completed July 2012);
o the new theatre stage ( completed in December 2012); and
o the relocated Peace Garden (partially completed in 2012)
Phase 3 is targeted for completion by the middle of 2014:
o increased landscaping along the western edge of the Square - completion by end of
2013;
o completion of deferred work related to the relocated Peace Garden – completion by
end of 2013;
o new planting and landscaped surfaces for the Queen Street frontage of the Square;
and
o upgrading the existing building at the corner of Queen and Bay Streets;
Phase 4 is targeted for completion by the end of 2014:
o Bay Street streetscape; and
o Upgrading the underground PATH pedestrian walkway.
The proposed new restaurant will be constructed separately (tentatively scheduled for
2013-2015), based on a Request for Proposals selection process and a business case to
lease the restaurant to a private restaurant operator.
Renovation of the Ceremonial Ramp is being constructed separately as part of the State
of Good Repair scope of work and is scheduled for completion at the end of 2019.
Project Elements and Schedule
The NPS project construction (including revitalization and State of Good Repair (SOGR) work) is divided into four phases with various project elements scheduled for completion from 2010 to 2014 and is summarized as follows:
Phase 1A was completed in May 2010 with the construction of the new City Hall
Podium Green Roof.
Phase 1 was completed in 2010-2011 as follows:
o replacement of the children's playground equipment (completed December 2010);
o new Skate Pavilion and Concession building (completed November 2011); and
o underground infrastructure work for other project elements, including electrical,
data, water, sewer, and gas site services (completed December 2011).
Phase 2 was completed in 2012 as follows:
o the new northwest vehicular laneway (completed February 2012);
o a nine-jet water fountain feature and new electrical and data hydrants in the middle
of the Square (completed July 2012);
o the new theatre stage ( completed in December 2012); and
o the relocated Peace Garden (partially completed in 2012)
Phase 3 is targeted for completion by the middle of 2014:
o increased landscaping along the western edge of the Square - completion by end of
2013;
o completion of deferred work related to the relocated Peace Garden – completion by
end of 2013;
o new planting and landscaped surfaces for the Queen Street frontage of the Square;
and
o upgrading the existing building at the corner of Queen and Bay Streets;
Phase 4 is targeted for completion by the end of 2014:
o Bay Street streetscape; and
o Upgrading the underground PATH pedestrian walkway.
The proposed new restaurant will be constructed separately (tentatively scheduled for
2013-2015), based on a Request for Proposals selection process and a business case to
lease the restaurant to a private restaurant operator.
Renovation of the Ceremonial Ramp is being constructed separately as part of the State
of Good Repair scope of work and is scheduled for completion at the end of 2019.