    Line 5 Condos (Reserve Properties/Westdale Properties) - Real Estate -

    My interim occupancy got pushed to Oct 31 for now
  2. A

    Toronto Line 5 Condos | 113.99m | 39s | Reserve Properties | Arcadis

    I’m in the north tower and mine got pushed to August 2024! Expecting another delay given their current speed
  3. A

    Toronto Line 5 Condos | 113.99m | 39s | Reserve Properties | Arcadis

    Hopefully they’ll finish the roof on both towers before the year ends
  4. A

    Line 5 Condos (Reserve Properties/Westdale Properties) - Real Estate -

    I don’t think so, I wouldn’t know if there is a website to track or somewhere to call the city to get update on the completion of the project
  5. A

    Line 5 Condos (Reserve Properties/Westdale Properties) - Real Estate -

    your interim occupancy might happen before the builder completely finishes the construction, but they won’t be able to transfer the title to you before the final inspection is done by the city which is after completion of the construction.
  6. A

    Line 5 Condos (Reserve Properties/Westdale Properties) - Real Estate -

    Official tentative occupancy date is Nov 2023. But realistically it’d be Q3 or latest Q4 2024. They’re just pouring the 10th-11th floor and if they start moving the project along faster, they’ll be able to pour a floor every 2 weeks
  7. A

    Toronto Line 5 Condos | 113.99m | 39s | Reserve Properties | Arcadis

    Thanks a lot, they might be pouring the pool in the middle now
  8. A

    Toronto Line 5 Condos | 113.99m | 39s | Reserve Properties | Arcadis

    Hi, I was wondering if someone is kind enough to post some new photos of the construction? I recently moved away and can't drop by that easily anymore. I was curious if they finished the north and south podium yet? Thanks a lot