News   Mar 28, 2024
 531     0 
News   Mar 28, 2024
 410     1 
News   Mar 28, 2024
 750     0 

Search results

  1. A

    Mississauga The Orchard District | ?m | 25s | GALA | BDP Quadrangle

    The decision summary from the OLT Settlement Hearing is now available. It appears that the City accepted the revised proposal outlined in my post from September 15, 2023.
  2. A

    Mississauga 4615 Hurontario | 156.4m | 45s | Elia Corp | BDP Quadrangle

    The Merit Hearing was cancelled, and a Settlement Hearing has been scheduled for March 21, 2024
  3. A

    Mississauga 1000 Dundas Street East | 70.4m | 20s | Ahmed Group | WZMH

    Merit Hearing is scheduled to commence on April 29, 2024
  4. A

    Mississauga Dundas & Mattawa | 138.5m | 41s | Hazelview | SvN

    Another Case Management Conference was held on February 28, 2024, with an additional conference scheduled for October 16, 2024, and a merit hearing scheduled to commence on March 24, 2025.
  5. A

    Mississauga 971 Burnhamthorpe Road East | 23.55m | 6s | Reza Tahmasebi | Icon

    This was considered at the Planning & Development Committee meeting held on January 8, 2024 (item 6.1 of the agenda, here). The Recommendation Report (included in the agenda package) concluded: "In summary, Council’s 2016 approval should be upheld, as the proposal represents an appropriate form...
  6. A

    Mississauga 1041 Lakeshore Road East | 33.04m | 10s | Skybourne | RAW Design

    The Public Meeting Recommendation Report (here) concluded that "the proposed development maintains the goals and objectives of the Lakeview Local Area Plan and represents an overall built form that is compatible with the surrounding neighbourhood. The proposed official plan amendment and...
  7. A

    Mississauga The Miss Queen | 36.9m | 9s | Lamb Dev Corp | A&Architects

    Per the memo summarizing the Case Management Conference held on October 10, 2023 (here), a nine-day hearing has been scheduled to commence on March 18, 2024.
  8. A

    Mississauga 805 Dundas Street East | 49.85m | 12s | KJC Properties | Kirkor Architects

    This item will be discussed at Mississauga's next Planning and Development Committee meeting on January 22, 2024 (public meeting notice).
  9. A

    Mississauga 170 Lakeshore Road East | 56.6m | 17s | Lightpoint | Arcadis

    Per the memo summarizing the status hearing held on November 30 (here) the project is back to being described as a 15-storey mixed-use building, including a 6-storey podium. A six-day hearing has been scheduled to commence on Monday, April 15, 2024.
  10. A

    Mississauga 30 Eglinton Avenue West | 113m | 34s | Plaza Partners | BDP Quadrangle

    It was appealed to OLT for the standard reason (City's failure to make decisions within the prescribed statutory timelines set out in the Planning Act). With respect to your second question, the memorandum of the oral decision delivered on October 27, 2023 noted that the Tribunal agreed with the...
  11. A

    Mississauga Six Five Agnes | 98.3m | 29s | Intentional Capital | Sweeny &Co

    OLT Case # OLT-23-000761. The first case management conference was held on November 7, 2023; a second case-management conference is scheduled for January 11, 2024. A 9-day Merit Hearing will commence on Monday June 17, 2024.
  12. A

    Mississauga 1000 Dundas Street East | 70.4m | 20s | Ahmed Group | WZMH

    The Merit Hearing has been adjourned. A revised date for the hearing has not yet been posted on the OLT website.
  13. A

    Mississauga Westminster United Church Redevelopment | 43.8m | 12s | UPRC | KPMB

    A revised submission in October 2023 calls for two 12-storey residential buildings containing 250 residential units. 100% of the units are proposed to be rental, with 30% targeted to be affordable rental.
  14. A

    Mississauga 42-46 Park Street East | 79.24m | 22s | Edenshaw | Arcadis

    The Decision Summary from the OLT Merit Hearing has been posted. The OLT dismissed Edenshaw's appeals. It was agreed that the property is a good candidate for intensification, and is currently underutilized. However, the Tribunal noted that the proposed development of 24 storeys would make it...
  15. A

    Mississauga Connecting Cooksville | 154.1m | 46s | TAS | SvN

    A Status Hearing is scheduled for August 2, 2024, and a Merit Hearing is scheduled for September 16, 2024.
  16. A

    Mississauga 70 Park Street East | 131.3m | 38s | Dream | Arcadis

    No written summary of the OLT Case Management Conference held on October 25 is available yet, but a merit hearing has been scheduled to commence on May 6, 2024.
  17. A

    Mississauga 128 Lakeshore Road East | 30.5m | 8s | Blacktusk Group | Arcadis

    Following the Settlement Hearing held on October 17, 2023, the OLT ordered the approval of the revised redevelopment proposal (an eight-storey (26 metres) mixed-use building, plus one technical storey (4.5 metres), providing 37 residential units, a total building Gross Floor Area of 5,064 square...
  18. A

    Mississauga 170 Lakeshore Road East | 56.6m | 17s | Lightpoint | Arcadis

    The Merit Hearing on October 30, 2023 was adjourned. A Status hearing is now scheduled for November 30, 2023.
  19. A

    Mississauga The Orchard District | ?m | 25s | GALA | BDP Quadrangle

    The City accepted the revised plan. The merit hearing planned at the OLT on November 14 has been changed to a settlement hearing.
  20. A

    Mississauga 60 Dundas Street East | 106.97m | 29s | Almega | Chamberlain

    This project is on the agenda for the Planning and Development Committee Meeting scheduled for October 23. The City's Recommendation Report concludes that "the development, as proposed, is not acceptable from a planning standpoint and should not be approved. While staff support an increase in...

Back
Top