  1. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    They have poured the slab for level 67, including the columns that will support level 68:
  2. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    The corner anchors were installed today, for the diagonal beams..
  3. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    From today. They are laying the forms down for level 67.
  4. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    From today. Some concrete pour happening at the top:
  5. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    From today. The forms for the concrete being placed in the corners at the upper mechanical level. Also, the columns at the top are being poured:
  6. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    I believe they are pouring level 65 today. The corners at level 57 was poured yesterday.
  7. BloorMan

    Toronto 11 YV | 213m | 62s | Metropia | Sweeny &Co

    From today:
  8. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    Here are some pictures from yesterday and today. The 65th floor looks like it's almost ready to get poured. The forms and electrical conduits have been installed. I can't see the concrete nozzle at the top anymore from my level :(
  9. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    From today. They are pouring the columns and I confirmed that the finished slab is level 64.
  10. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    Some crane parts getting hauled up this evening:
  11. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    Here are a couple shots from North York (Keele & 401 area):
  12. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    Looks like the extra crane section wasn't added in yesterday after-all. Today was the day:
  13. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    The top crane brace is secured to the floor of level 60, as per the markings on the wall. It's hard to say for sure if the last floor poured is 64 or 65. What does everyone think?
  14. BloorMan

    Toronto 11 YV | 213m | 62s | Metropia | Sweeny &Co

    From this Friday evening:
  15. BloorMan

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    From today, they added a crane support at level 60. In fact, they are still working on it as of 8pm this evening. Benito's pictures show a section of crane being hoisted and most likely that was inserted too.