    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    Wednesday June 26, 2024
  2. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    June 07, 2024 Good day, here are some updated pictures from my viewpoint, taken just now
  3. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    May 1st, 2024 It's been a while since I last posted photos, here are some taken just now
  4. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    So the crane was fully assembled Friday. Here are some pictures taken just now. On the last picture, you will see a new generator (right next to the front of the truck). This was brought in to power the crane. When in use, it is very loud and sounds like a truck is parked right underneath my...
  5. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    January 16, 2024 It appears portions of the crane are being installed this week. Pieces have been delivered and setup since yesterday and they use the back of the former Girl Guides office (recently closed and vacated) as a staging area for the large trucks to pull into, therefore Merton has...
  6. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    February 15, 2024 Crane base installation continues..
  7. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    February 6, 2024 More concrete!
  8. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    Another taken just now to show how quick things are progressing
  9. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    January 30, 2024 Crane base prep work progressing.
  10. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    I’m back and posting a couple pictures of the site with the poured concrete.
  11. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    I’m out of the country, so can’t post views from my side, but will provide an update when I’m back. If I recall, the crane installation was to begin end of January, which is on track. https://www.30mertondevelopment.com/
  12. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    Updated pictures taken just now (December 21, 2023). It appears as the Bell utility box was removed yesterday. The Rogers cable as well as a Gas one remain there for now.
  13. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    November 28, 2023 A few updated pictures as we wrap up November. Activity has been ramping up in the past few weeks in preparation for the crane installation next month, I believe.
  14. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    October 25, 2023 update: Changes since last time: - Concrete barricades were installed on Merton, blocking part of the sidewalk as it is used for their own equipment and material. (Likely to be expanded as construction progresses, especially when crane is installed) - Bottom seems to have been...
  15. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    October 11, 2023 A few changes in the past few days: 1. Concrete barriers were installed on Merton yesterday. 2. Excavation has begun at the site of the original ramp, so a new ramp was built on the South Eastern side of the site. 3. Developer site says that hoarding work (concrete beams...
  16. W

    Toronto 30 Merton Street | 125.3m | 37s | QuadReal | Sweeny &Co

    September 27, 2023 Excavation continues (and getting quite deep, especially at the north-west end). Picture taken minutes ago: