  1. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    Because they need a doorway. It is not for the elevator core, it is to be able to pour regular repeating typical walls above.
  2. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    makes sense the small cut out is for the 2 chutes, the room itself is of course poured.
  3. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    I believe those were just temporary stiffeners to keep things square prior to pouring since it was 50 feet high thin metal.
  4. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    i wonder what the unpoured areas near the elevators are for
  5. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    Well now we are into regular type slabs... i bet we see the next vertical pour within 14 days
  6. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    No they poured the rest of the rooftop you can see the wet concrete
  7. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    That is top of the podium tho.. it doesnt go higher.
  8. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    you would want the floor to support the diagonals to not flex the columns
  9. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    They need to be strong to hold the concrete in when it is wet. People die or get super hurt all the time when the forms are pulled off and hanging by 1 bolt and fall on them
  10. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    crazy that much weight ( forms weigh like 3000lbs each) can be hanging off the side of the building held in by some shots...
  11. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    yes just usually the pour is far ahead
  12. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    nothing else is this complex.
  13. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    they told me they will have at least 1 floor every 2 weeks, which seems slow still but much faster... hopefully they can get that speed upto a floor a week.
  14. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    Looks like they on schedule for the pour on 15th
  15. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    I was told that after this floor, additional floors will be about 1 every week - 2 weeks.
  16. J

    Toronto The One | 328.4m | 91s | Mizrahi Developments | Foster + Partners

    Going to be 1000 cubes in the pour. date is october 15