Toronto Porsche Centre Downtown | 12.76m | 3s | DFC | BDP Quadrangle

Today:

1775332214234.jpeg

1775332230439.jpeg

1775332245367.jpeg
 
That certainly doesn’t look 3 weeks from opening day..
They're moving quick, but I agree, I think they will still need at least another week before it would be ready assuming they keep at the pace they've gone over the last two weeks. From the first shot below, they still don't even have interior drywalling done - you can see insulation hanging.

That said, they're so confident they already have cars in the back lot.

From last night:

Let there be light!

tempImageoQn9jo.jpg
tempImagenZmmuB.jpg


Though....even without the full light show, I'm concerned with what it does to this new neighbourhood - this shot taken with zoom from Don Roadway and Commissioners:

tempImageIRJxgi.jpg
 

Back
Top