March 17
As it stands today, there are there are 15 intersections that still require a guideway built across them that will take 1-2 months to do them. Expect to see 2-3 intersections being done at the same time, but not in a row.
One month
Brampton: Lancashire, Sir Loo, Courthouse/Shopping Plaza,
Mississauga: Fairview, John St, Kingsbridge, Paisley
Two months
Brampton: Fire Station, Ray Lawson.
Mississauga, Station Gate, Hwy 403 to the elevated section, Dundas St, North Service Rd, QEW Off/On ramp for westbound, South Service Rd/QEW eastbound off/on ramp, Pinetree, Pinewood?, Centre of Hurontario to the west side guideway.
I expect Fairview and Paisley will be the next two full closure that will happen either this month or early April that will take one month each. Trackwork on both side of the intersection not currently in place will be done at the same time of the intersection trackwork.
Both Pinetree and Pinewood could be done as one month closer requiring longer driving distance. Station Gate will be a problem for GO Transit buses as they need to do a right turn in and left turn out let alone traffic unless GO use a temporary bus bays in the parking lot using City View for in/out with full closure of Station Gate for one month.
The remaining guideway construction is still on schedule to be completed by September if not sooner. Trackwork will be completed by the fall. The elevated section should be completed by the fall as well.
There are still 5 stations to be built plus the Mineola partly built at this time.
All the sidewalks from end to end still has to be built and that will be completed in 2027. Road repaving should happen in 2027 along with all intersection new traffic lights in full service
The overhead system is an unknown timeframe
If you look at
@khaldoon photo, you will noticed a number of things beside the substation. Trench work has stated in the northbound curb lane now the hydro poles are gone as well the curb work from the restraining wall to Englewood before going north for the plaza area. You can see the new sidewalk light post with sidewalk still missing. The base of the Station guideway still needs to be pour and don't recall seeing any duck banks being installed in 2025. Until the duck bank is in place, the base cannot be pour as well laying of the trackwork that will include a crossover.
As for the Mary Fix Creek, I found it odd that the wall to the north and west of the curve is higher than the curve when it was built in 2024. The new spillway is 2.5 times wider than the existing one as well deeper with a deeper section under the water in place now. This will handle a 100 year event with no problem as the water and the water level will increase as it exit the current narrow area to the north as well the 90 degree bent as going under Hurontario St .The water flow will decease as it flow toward the curve as the spillway becomes wider
There are two pad areas with one north of the CPKC bridge and the other south of Derry Rd for emergency vehicles. They are also found on Line 5 & 6 as well. The pad north of the bridge cannot be use as a crosswalk from the east side to the west side as there is a retraining wall preventing access to the west sidewalk that is about 7 feet above the road with no stair or ramp to it.