After asking repeatedly, I finally wore them down: How far behind are they at Osgoode station? “Two months”. The original schedule called for excavation completion by end of March. Now it’s end of May.
Honestly, given how behind things seem to have been, 2 months isn’t bad. It was clear how much they were hustling and to catch up in the excavation phase.
I didn’t get an answer for my more important questions: how long will the acoustic tent be up for and when can they begin to restore Osgoode Garden?
The answer to the second question is semi-dependent on The Law Society who will receive funds from Metrolinx to restore the garden but will be responsible for designing and landscaping it. But when will the lands be returned? Nobody wants to give me a date.