One thing I would also note from that collection of documents (there are 7 in total) is that the Cooksville Creek bridge on the Lakeshore West line is up for replacement next year. This is notable for 2 reasons.I created a table comparing the September and December 2025 Capital Projects Group pipeline documents.
2025Q3 Status2025Q4 Status Portfolio Line Project Prequalification RFP Awarded MERX Estimated RFP Date GO Expansion Stouffville Mount Joy Station Improvements, Passing Track and Signals: Construction of passing track, a new side platform and associated infrastructure, and signals work including installation of new turnback signal near Stouffville GO. Dec-22 Upcoming 2025Q4 2026Q4 (delayed one year) GO Expansion Stouffville Stouffville Existing Station Renovations: Upgrades to various existing GO stations in the Stouffville corridor including civil work (e.g., parking lot improvements, bus loop restoration, station building retrofits and platform upgrades including
accessibility upgrades).Dec-22 Upcoming 2026Q1 2026Q1 (unchanged) GO Expansion Stouffville Kennedy GO Station: West Platform Extension and Trackwork. TBD TBD Project Removed GO Expansion Barrie Barrie Existing Station Renovations: Upgrades to various existing GO stations in the Barrie corridor including civil work (e.g., parking lot and bus loop improvements, station building retrofits and platform upgrades). Dec-22 Upcoming 2026Q1 2026Q1 (unchanged) GO Expansion Barrie West Toronto Rail Path Extension (South of Dundas Street on the Barrie Corridor): Grading work, along with construction of four new, multi-use path bridges and several community connections. TBD TBD 2026Q2 (new date) GO Expansion Barrie Bradford Station: West Platform Construction and Layover Modification. TBD TBD Project Removed GO Expansion LSE Lakeshore East Existing Station Renovations: Upgrades to various existing GO stations in the Lakeshore East corridor including civil work (e.g., parking lot and bus loop improvements, station building retrofits and platform upgrades
including accessibility upgrades).Dec-22 Upcoming 2026Q1 MERX Project Tender July 2025 2026Q1 (unchanged) GO Expansion LSW Lakeshore West Existing Station Renovations: Upgrades to various existing GO stations in the Lakeshore West corridor including civil work (e.g., parking lot improvements, bus loop restoration, station building retrofits and platform
upgrades including accessibility upgrades).Dec-22 Upcoming 2026Q1 2026Q1 (unchanged) GO Expansion LSW Niagara Falls Layover Facility: Construction of a single-track layover facility for train storage, along with signals and track work. TBD TBD Project Removed GO Expansion RH Oriole GO Station Relocation: Improved station access, customer safety and customer experience. TBD TBD Project Removed GO Expansion KI Kitchener Line Extension | Guelph Subdivision Package 4: Track and signals work, platform work, grading, drainage, and utility relocations in support of Kitchener GO service extension. Apr-24 Upcoming 2026Q1 2026Q2 (delayed one quarter) GO Expansion KI Kitchener Central Transit Hub: Construction of a GO station that is part of multimodal transportation hub in the Waterloo Region. Construction of track realignment, switch, station platforms, tunnels and associated civil works to support a Region-led initiative for a new multi-modal transit hub in Waterloo Region. Dec-25 Upcoming 2026Q1 MERX Prequalification November 2025 2026Q2 (delayed one quarter) GO Expansion KI Mount Pleasant GO Station Modifications: Renovations including removal of the north platform to create space for a future track and modifications to existing tunnels, north stairs, and elevator. N/A TBD 2027Q4 (new date) GO Expansion KI Kitchener Extension | Guelph Subdivision Package 2A: Track and signals work, grading, drainage, and utility relocations in the Town of Halton Hills (Acton) in support of Kitchener GO service extension. Apr-24 TBD 2026Q2 (new date) GO Expansion KI Georgetown GO Station Improvements & Layover (Phase 1): Construction of a new island platform, bus loop, passenger pick-up and drop-off area, and a pedestrian bridge. TBD TBD 2027Q4 (new date) GO Expansion KI Georgetown GO Station Improvements & Layover (Phase 2): Extension of the pedestrian bridge from the island platform to the North parking lot, removal of layover tracks and rehabilitation of the parking lots. TBD TBD 2027Q4 (new date) GO Expansion KI Kitchener Line Extension | Guelph Subdivision Package 3: Bridge reconstruction, grading and drainage for passing track extension, track and signals works, retaining walls, and trenchless twin culverts. TBD TBD Project Removed GO Expansion Toronto Technical Services for both task based and highly skilled individuals. 2026Q2 (new entry) GO Expansion Toronto Program Oversight (Auditing, Analysis, Assurance) for non-conflicted entities, performing audit and oversight functions. 2026Q2 (new entry) GO Expansion Toronto CMS - Commercial Management System. 2026Q2 (new entry)
First, currently there is no foot path under that bridge, and I haven't heard any consultations about adding one. A trail underneath the new bridge would be good in and of itself for connectivity to the waterfront.
Second, the Revus Avenue level crossing is just 300 metres to the west, and that crossing may be permanently closed in the next few years. If the Revus crossing closes, I imagine it will need to be replaced by a pedestrian crossing. I'm not entirely a fan of closing the Revus crossing permanently, but in case it does, they should do some consultations about whether a path under Cooksville Creek could substitute for a pedestrian bridge at Revus. (EDIT: A pedestrian bridge at Revus could add several hundred metres of walking if it's anything like the new Drury Lane one, so a path at Cooksville Creek might even be a similar walking distance, even accounting for the 300 metres there and back.)
(Second EDIT: A screenshot of the existing Cooksville Creek bridge from Google maps.
)