Mississauga Dixie Rd/QEW New Interchange (MTO, 1s, AECOM)

Nov 16

The eastbound on/off ramps were paved on Saturday but the QEW eastbound 4th lane and off ramp lanes are not completed been pave.
 
Nov 22
Major shift for eastbound traffic is about to happen as the new off/on lanes as well the 4th lane is all paved and strip. No stripping for the ramps yet.
 
Nov 27
No shifting of the eastbound lanes yet as they were paving at the far east end today. Saw no striping for the ramps.
 
Dec 5
The 4th lane is ready to be opened eastbound, as the concrete barriers have been moved to near the sound barrier wall and are blocking off the off-ramp to Dixie Rd. Pillows are currently blocking off access to the 4th lane.

The current eastbound off-ramp lane from Cawthra to the QEW will become the 4th lane when the 4th lane opens. The new on-ramps to the QEW from Dixie Rd are striped, with work still taking place for the eastbound off-ramp to Dixie Rd.

The 4th lane may open this weekend or the next 2 weekends once work is done for the off-ramp. Hard to say if the westbound on-ramp from Dixie Rd will open this year or until the new centre barrier is built.

Still a lot of work for the North Service Rd sound barrier wall at Ogden overpass.
 
Dec 5
More up on my site
All the concrete barriers have been removed and relocated next yo sound barrier walls as well for off/on ramps for Dixie with pillions replacing the barriers. Don't know if the new lanes have been open as they were not a week ago.

The on ramp from Cawthra will continue into the 4th lane when it opens and will improve the traffic flow at that point than the current slow down for merging.
54983548922_cd3a5f1c16_o.jpg

54984719945_72cf43444c_o.jpg

54984677004_70cc8328b1_o.jpg

54984719925_b2b3333493_o.jpg

54984677009_bc7c817538_o.jpg

54983548842_487076b630_o.jpg

54984676939_338ae44ec2_o.jpg
 

Back
Top