Metrolinx has posted a whole bunch of quarterly reports from its upcoming board meeting on Nov. 27 on
its documents page. There is way too much to summarize, but here are a few noteworthy things.
- The Finch West LRT will start revenue service on Dec. 7.
- The Scarborough Subway tunnel boring machine has tunnelled 3 km and is undergoing another planned maintenance stop south of Brimorton Dr.
- ECTS is being tested on the Richmond Hill Line.
- The Etobicoke Creek Bridge replacement on the Lakeshore West Line is expected to be done by the end of December.
- On the Kitchener Line, work with CN has progressed to detailed design on corridor upgrades.
There is a lot more in those documents. I have downloaded copies of the reports in case any of the 12 board meeting documents get pulled.