Those 6 LRVs that are in the yard are there as there is no room inside for them as it is full of other LRVs and no numbers for them.
How Many intersections will see tracks rebuilt??? Courtneypark intersection that supposed to be done by November 4th is currently one of 5 that has to be done that is known at this time,
Topflight intersection is supposed to be open on October 15. Rails are 100% installed as well being splice with more to take place. All splicing should be done next week that concrete nay start to take place,
The OMSF guideway still being built with part of the south end tracks encased ib xoncrete, No idea what still has to be done for the east-west section.
Part of the curb is poured for the westbound ramp to the 407 on the northside of the bridge. as well betwwen it and the off ramp. Paving still to be done for the north end except between the two ramps. More concrete curb work still has to be done for Hurontario and the eastbound ramp, otherwise the northbound lanes can open early October.
Fail to check Derry Station work and did not look at Brampton area at all.
There is a large slab area south od Derry with fencing around it that you no isea what is taking place going north. Going south you can see concrete removed from the encased northbound track.
Queensway platform is formed and ready for concrete pour.
Aeron crew working on wiring for a pole that may have cable going underground north of the Morth Service Rd and fail to stop on my way back from Port Credit.
All the steel mats in place for the southbound track south of Fairview. Look like a 2 man crew doing something between CP ans Fairview and were sitting on the rails as I drove by.
Forming and pouring of the WYE base is taking place as you can see the formwok from Hurontario as well the eastbound off ramp to Hurontario.
Very large hole on the north side where the 403 ramp will connect to Hurontario qs well part of the area where the fome bkocks are to go for the ramp.
My plan for today was to do some video shooting of a few areas as well the whole corridor but the new camera either has an issue or all 3 batteries for it were dead considering I have yet to use the spare batteries that were charge over a week ago. It kill the video shooting and try using the Mark II with poor luck as it refused to stay in fouces. Best to do the video shooting is around 8 am on Sunday when traffic is light and also when the sunrise is happening these days.
Photos to follow
Sept 26
You can see the poles that need to be removed before roadwork and curbing can take place for the northbound lane. It been this way since 2023.
Those 6 LRVs that are in the yard are there as there is no room inside for them as it is full of other LRVs and no numbers for them.
How Many intersections will see tracks rebuilt??? Courtneypark intersection that supposed to be done by November 4th is currently one of 5 that has to be done that is known at this time,
Topflight intersection is supposed to be open on October 15. Rails are 100% installed as well being splice with more to take place. All splicing should be done next week that concrete nay start to take place,
The OMSF guideway still being built with part of the south end tracks encased ib xoncrete, No idea what still has to be done for the east-west section.
Part of the curb is poured for the westbound ramp to the 407 on the northside of the bridge. as well betwwen it and the off ramp. Paving still to be done for the north end except between the two ramps. More concrete curb work still has to be done for Hurontario and the eastbound ramp, otherwise the northbound lanes can open early October.
Fail to check Derry Station work and did not look at Brampton area at all.
There is a large slab area south od Derry with fencing around it that you no isea what is taking place going north. Going south you can see concrete removed from the encased northbound track.
Queensway platform is formed and ready for concrete pour.
Aeron crew working on wiring for a pole that may have cable going underground north of the Morth Service Rd and fail to stop on my way back from Port Credit.
All the steel mats in place for the southbound track south of Fairview. Look like a 2 man crew doing something between CP ans Fairview and were sitting on the rails as I drove by.
Forming and pouring of the WYE base is taking place as you can see the formwok from Hurontario as well the eastbound off ramp to Hurontario.
Very large hole on the north side where the 403 ramp will connect to Hurontario qs well part of the area where the fome bkocks are to go for the ramp.
My plan for today was to do some video shooting of a few areas as well the whole corridor but the new camera either has an issue or all 3 batteries for it were dead considering I have yet to use the spare batteries that were charge over a week ago. It kill the video shooting and try using the Mark II with poor luck as it refused to stay in fouces. Best to do the video shooting is around 8 am on Sunday when traffic is light and also when the sunrise is happening these days.
Photos to follow
Sept 26
You can see the poles that need to be removed before roadwork and curbing can take place for the northbound lane. It been this way since 2023.