Toronto 50 Wilson Heights Blvd | 55.47m | 16s | Greenwin | Kirkor Architects

While there has been yet more slippage, this one looks like it has a firm launch date.

June '24.

Given the nearness and a pending meeting with CMHC (firm date) this is big, as this is a very large project to get off the ground, even if it is very late.

All that from this report to the next meeting of CreateTO:


1713188730485.png


* grumble *

I do not see any building permit applications filed.

If they want to really (not ceremonially) break ground in June those need to have been filed by now...... sigh. Amateur hour continues.
 
Thanks for posting. Once this gets built there will be 4,713 units here built in the last decade which will be just over 9,000 residents. A true TOD if I ever saw one! Basically a new neighbourhood.
 
An update on this one, in the latest report to CreateTO:


1718289459244.png

1718289477582.png


So....we're modestly (further) delayed here...........but CMHC was yesterday maybe we can confirm the outcome of that, if that's a go then we are a step closer.

There are, however, still, no permit applications.

I'm going to say right now that all but rules out a start before Labour Day. It would require very expedited service from buildings. I'm not clear on why these have not been filed.

CMHC's approval is not required to file for permits.
 