Recent content by Frankietls

  1. F

    Toronto Ontario Line 3 | Metrolinx

    There will be 13622 precast liners in total for the southern tunnel, of which 1900 has been delivered to temporary storage site in Uxbridge. I'm seeing in the system 6 delivered on site at Exhibition and all installed. Either they're doing a trial or the tracker is not up to date. At Exhibition...
  2. F

    Toronto Ontario Line 3 | Metrolinx

    They have installed the first ring (6 precast segments) as of this morning. I tried to find some visual proof but no luck.
  3. F

    Toronto Ontario Line 3 | Metrolinx

    It was actually "launched" yesterday, they had to do it because it's a contract milestone . They just made sure the TBM can rotate properly, monitored the thrust frame structure and had everything working.
  4. F

    Toronto Ontario Line 3 | Metrolinx

    TBM travelling speed is scheduled at 17-20m per day.
  5. F

    Toronto Ontario Line 3 | Metrolinx

    It's Corktown, not Moss Park, a typo from me.
  6. F

    Toronto Ontario Line 3 | Metrolinx

    Pretty typical for any type of consultancy quotation, the formula goes like this: (Number of changed drawings x billable hours per drawing) x (Jr Drafter rate + Sr Drafter rate + Engineer/Architect rate + Lead Engineer/Architect rate + Project Coordinator rate + Project Manager rate + Director...
  7. F

    Toronto Ontario Line 3 | Metrolinx

    On another note, TBM launch date is April 23rd.
  8. F

    Toronto Ontario Line 3 | Metrolinx

    Price tag for the name change: - Corktown: $200,000 - Queen Spadina + King Bathurst: $170,000 - Riverside-Leslieville: unknown - Other stations (indirect impact): $60,000 Please don't ask why the numbers don't add up. They are from each station designer's quotation.
  9. F

    GO Transit Electrification | Metrolinx

    From a project management point of view, this means the System & Intergration contractor is involved and their design has evolved to the point where 3D model is provided for coordination. Architectural designer can not add OCS to renders out of thin air. Doesn't tell much about timeline but also...
  10. F

    Cycling: West Toronto Railpath (City of Toronto, Phase II Proposed)

    I think you are right. Found the same design for the pier of the pedestrian bridge at Bloor as part of the Barrie line MUP. I believe this is the Construction Notice for that pier next to No Frills, predate the one I posted above.
  11. F

    Cycling: West Toronto Railpath (City of Toronto, Phase II Proposed)

    Also found this Construction Notice, looks like the Rail Path Extension is really coming this time. https://assets.metrolinx.com/image/upload/v1775136253/Images/Metrolinx/Toronto West/Barrie_Rail_Corridor_Improvements_April_17.pdf
  12. F

    Cycling: West Toronto Railpath (City of Toronto, Phase II Proposed)

    The location of the first pier doesn't line up with the bridge drawing.
  13. F

    Toronto Ontario Line 3 | Metrolinx

    The bridge looks nice. It serves its intended design purpose. The roadway underneath it was only closed for one Saturday during construction. I don't understand what triggered the anger that last 2 pages ?
  14. F

    Toronto Ontario Line: King West Station | 10m | 1s | Metrolinx | HDR

    The RFQ is from the contractor, not Metrolinx. Believe it or not there is no expertise in North America for this, and yes it has to be custom built. Each supplier even has different design. 2 Italian suppliers with manufacturing facilities in Indonesia and India, 1 Spanish supplier with...