Toronto SQ Spadina Queen Condos at Alexandra Park | 43.89m | 14s | Tridel | Teeple Architects

Picture 2.png

Picture captured by Tridel's webcam on Tuesday, November 17th. The construction in the foreground is the TCH/Atkinson Co-op townhouses. Tridel's SQ condo is located behind. They are currently working on the third floor.
 

Attachments

  • Picture 2.png
    Picture 2.png
    756.5 KB · Views: 2,486
Last edited by a moderator:
Picture 1.png

Picture captured by Tridel's webcam on Tuesday, December 15th. The construction in the foreground is the TCH/Atkinson Co-op townhouses. Tridel's SQ condo is located behind. They are currently working on the fourth floor.
 

Attachments

  • Picture 1.png
    Picture 1.png
    782.2 KB · Views: 2,396
Last edited by a moderator:
Picture 1.png

Picture captured by Tridel's webcam on Tuesday, January 19th. The construction in the foreground is the TCH/Atkinson Co-op townhouses. Tridel's SQ condo is located behind. They are currently working on the fifth floor.
 

Attachments

  • Picture 1.png
    Picture 1.png
    745.2 KB · Views: 1,845
Picture 2.png

Picture captured by Tridel's webcam on Friday, February 19th. The construction in the foreground is the TCH/Atkinson Co-op townhouses. Tridel's SQ condo is located behind.
The construction team is pouring concrete on the 7th floor. Plumbing and electrical rough-ins have started on the 2nd floor with the installation of piping, ductwork and wiring.
 

Attachments

  • Picture 2.png
    Picture 2.png
    729.6 KB · Views: 1,465
Picture 1.png

Picture captured by Tridel's webcam on Wednesday, March 16th. The construction team at SQ is currently pouring concrete on the 9th floor. Window installations have started on the ground floor and rough-in work for electrical and plumbing is on the 3rd floor.
 

Attachments

  • Picture 1.png
    Picture 1.png
    740 KB · Views: 1,091
Picture 3.png

Picture captured by webcam on Tuesday, April 19th. The construction team at SQ is currently pouring concrete on the 11th floor. Window installations have started on the 2nd floor and rough-in work for electrical and plumbing is on the 5th floor.
 

Attachments

  • Picture 3.png
    Picture 3.png
    774.8 KB · Views: 913
man, i can't wait to see the before/after on this entire housing project, will end up as some sort of north america-wide model for renewing public housing.
 