You're right Courtney, it's really a pain not having a realistic date. It is understood that there are many unknowns in the construction process but it would be far better to have an honest stab at an occupancy date than a hyper-optimistic one that keeps getting pushed. March 2012 is of course utterly impossible.
However now that the sub-grade work is almost done it should be much easier to give a realistic timeframe.
Are you folks at 5nine listening?
My guess is that first occupancies at the Kingeast will commence 12-14 months from now, so approx. Jan 2013. Anybody else willing to wager a guess?
This estimate is based on the construction progress of similar completed projects. Refer to my a post a few pages back giving some milestone dates for Lamb Dev Corp's - East Lofts which is very comparable in scope. (Post # 258 of Kingeast Proj&Const thread)