Mississauga Hurontario-Main Line 10 LRT | ?m | ?s | Metrolinx

20211206_110103.jpg

Looking north across Sq. One Dr. towards Rathburn and 403.

20211206_110231.jpg

Robert Speck and Hurontario.

20211206_110311.jpg

Looking south along Hurontario towards Absolute Ave. and Burnhamthorpe Rd. Looks like they're getting ready to dig up the road for water main replacement?
 
Is there a theoretical map of what hurontario would look like (including stations) with and without the loop
 
Is Aimco doing all of the surface level work?
BOT has been handling the roadway related work (curb/median removal & roadway widening) with Pave-Al Ltd handling the asphalt laying portion of the works.

I imagine BOT will be handling bridge structure work as they're big into that.

Amico has been handling all of the watermain and sewer relocation work to date.
 
Dec 11
The winds knock over the fence on Hurontario St at Port Credit that you had to walk on the road around it. The roof is not 100% form or seen concrete.
51740789121_c0e0e54933_b.jpg

51741023973_a7b7c004c3_b.jpg

51741023888_1932bbf5af_b.jpg

51741023838_fb2f13da43_b.jpg

51741675865_4f260c3c73_b.jpg

51741675805_8e23372e38_b.jpg

51741023838_fb2f13da43_b.jpg

51741675710_fed59c1ca8_b.jpg

51739965322_fcebfba209_b.jpg

51741023388_89c5ca4ac3_b.jpg
 
Operations Maintenance and Storage Facility (OMSF)
  • 3000 meters of rail delivered to the OMSF
  • 285,900 tonnes of backfill completed at the OMSF - over 2 times the weight of the CN Tower!


Hurontario Street Corridor
  • 2 times the height of Mount Everest's worth - 22,000 meters - of aerial conductor cable installed to run the LRT vehicles
  • 10,959 total square meters of sidewalks,curbs,driveway and pavement removed for lane widening on Hurontario
  • 1403 tonnes of new asphalt paved


579d6cd3-5082-e956-19b8-bf49139d3923.jpeg
A sneak peek inside the Operations Maintenance and Storage Facility (OMSF) building. (Metrolinx photo)​


6b460d64-e8ad-6947-8b1f-33abd472a5e9.jpeg
3,000 meters of track delivered to the Operations Maintenance and Storage Facility (Metrolinx photo)​


Wet & Dry Utilites and Sanitary Installations​



Construction crews will be continuing with the installation of new watermain and sanitary lines on Rathburn Road between Station Gate Road and just east of the Hurontario Street overpass.
Temporary lane closures will be required in this area from December 2021 to February 2022, including a third closure on Hammerson Drive (at Rathburn Road) in January 2022. Please look for signs announcing the lane closures on the roadway. Emergency access will always be maintained.
Overnight activities will be required at the two laydown areas located at Centre View Drive and Square One Drive beginning in December 2021. This work mainly involves trucks hauling construction materials from along the corridor and will continue until the construction is completed. Every effort will be made to minimize disruptions. Residents near the work site can expect to hear some noise from back-up beepers caused by trucks, excavators, and other construction equipment related to this work.
As utility works progress from west to east along Rathburn Road, there will be temporary road closures in order to install utilities that cross them. Please note that we will work to reduce the duration of these impacts, wherever possible, and we are working with adjacent property and business owners to provide advanced notice.
We encourage motorists to plan for delays. We recommend entering properties by turning right in, and exiting properties by turning right out. Please follow the signage in place and do not use private laneways and plaza parking lots as detour routes.


af17c4d2-b297-c320-14da-747fcc8e7b00.jpeg
Crews working to complete asphalt cutting for watermain installation (Metrolinx photo)​


COMING SOON IN 2022:​



What's Happening in January​



Over the past year, most medians have been removed and temporary traffic signals have been installed along Hurontario Street and Rathburn Road. This creates enough space for crews to reconfigure active lanes of traffic and allows them to safely relocate and upgrade utilities, while minimizing traffic impacts.
We have also begun work on building the foundation supports and caissons that will form the piers for the elevated guideway. The elevated guideway, otherwise known as the HWY 403 Flyover, will connect the LRT corridor along Hurontario to the Mississauga City Centre Transit Terminal once built.
In January 2022 , you can expect to see the following activities to take place in Mississauga Centre:
  • Relocations and upgrades to watermain, storm, and sanity infrastructure will continue along Rathburn Road and preparatory works for utilities will begin along Hurontario Street.
 