crs1026
Superstar
Remember, IO is the province's procurement agency. You won't see City-led and -funded projects on their list.
- Paul
- Paul
Doesn't seem the westside entrance of Mount Dennis will be opening anytime soon. The sidewalk access to the south facing entrance is blocked off coming from the west. Will that be opened in time for the station's opening?
Hopefully that's the case, but passing in front of the station that isn't obvious.I am pretty sure there is a sliver of a walkway there between the fencing and the station itself you can see in that picture that you can access just after the Scotibank on the corner that will lead you down to the station entrance.
That was precisely my concern. You can't expect folks to walk all the way to Black Creek and double back. There will be a ton of jaywalkers.I think there has to be because say you were outside that Scotiabank on the north side of Eglinton, to legally get to the other station entrance you would need to cross to the southside, then walk all the way down to Black Creek Drive and cross back to the Noth side and walk all the way back up to the other entrance! I did a very quick and dirty distance calculation on that walk and it is roughly 834 metres!
Hopefully that's the case, but passing in front of the station that isn't obvious.
That was precisely my concern. You can't expect folks to walk all the way to Black Creek and double back. There will be a ton of jaywalkers.
Why can't we ever get any fast tunnelling progress for the scarborough subway?Metrolinx has posted a slideshow update on the elevated guideway construction and tunnelling. The slide below stood out to me the most.
View attachment 695736
Which part of this (ECWE) project is TBM and which part is mined? I thought the vast majority was TBM.SSE seems to be a lesson in not using a single huge bore tbm in questionable soil conditions. The minned tunnel on ECWE is fairly slow but at least it is steady.
The part between Mount Dennis and the portal west of Weston Rd (~500 metres) is being SEM'd. The rest is TBM.Which part of this (ECWE) project is TBM and which part is mined? I thought the vast majority was TBM.
Yes, I suppose that bit is. Looks like only 300 metres from eastern end of the western portal, to Weston; not much longer than a subway station box.The part between Mount Dennis and the portal west of Weston Rd (~500 metres) is being SEM'd. The rest is TBM.